Weekly Reports
Financial Data (As of 18th September 2008 or 28th Sunbula 1387):
| Total block grant commitments for the CDCs Total block grant disbursements to the CDCs Total number of CDCs which have received block grants Total number of sub-projects financed minus changed sub-projects Total number of communities that have fully utilized their block grant entitlements Total number of communities that have completed subprojects for all their block grants Total block grant disbursements from 12/09 to 18/09/2008 (23/06 to 28/06/1387) |
$ 523,968,754 $ 509,199,837 18,318 37,320 4,116 3,841 $ 2,175,972 |
Source: NSP HQ Finance Department
Community Development Progress (As of 21st August 2008 or 31st Asad 1387):
| No of Communities which have been mobilized by the FPs No of Community Development Councils (CDCs) elected No of Community Development Plans (CDPs) completed No of Community sub-project proposals submitted to the NSP No of Community sub-project proposals approved by the NSP No of Community sub-projects completed |
21,962 21,605 21,277 43,189 41,741 23,035 |
Source: NSP Monthly Programme Report - Table 2
A multi-year impact evaluation study of phase two of the National Solidarity Programme (NSP) is underway
Community Participatory Monitoring (CPM) can be applied to a variety of development programmes and projects in rural areas. 